Case Study—50% Labor Reduction, 30% Time Savings, and No Damages, No Delays, No Change Orders—No Kidding! Application of 3D Subsurface Utility Engineering per ASCE 38 Standard for Puget Sound Energy’s SR-510 Gas Pipeline Project (English)
- New search for: Meis, Philip J.
- New search for: Haines, Donald W.
- New search for: Anderson, Shawnté
- New search for: Meis, Philip J.
- New search for: Haines, Donald W.
- New search for: Anderson, Shawnté
In:
Pipelines 2021
: Design
;
58-67
;
2021
-
ISBN:
- Conference paper / Electronic Resource
-
Title:Case Study—50% Labor Reduction, 30% Time Savings, and No Damages, No Delays, No Change Orders—No Kidding! Application of 3D Subsurface Utility Engineering per ASCE 38 Standard for Puget Sound Energy’s SR-510 Gas Pipeline Project
-
Contributors:
-
Conference:Pipelines 2021 ; 2021 ; Virtual Conference
-
Published in:Pipelines 2021 : Design ; 58-67
-
Publisher:
- New search for: American Society of Civil Engineers
-
Place of publication:Reston, VA
-
Publication date:2021-07-29
-
ISBN:
-
DOI:
-
Type of media:Conference paper
-
Type of material:Electronic Resource
-
Language:English
-
Source:
Table of contents conference proceedings
The tables of contents are generated automatically and are based on the data records of the individual contributions available in the index of the TIB portal. The display of the Tables of Contents may therefore be incomplete.
- 1
-
Alternative Delivery for Emergency Multiple Installation-Method Replacement of 30/36-in. Dual Steel Force Mains with FRPTrejo, Gilbert / Bowen, Jason / Ancell, Michael / Jenkins, Doug / Maine, Danny / Nuttbrock, Nancy et al. | 2021
- 10
-
Environmental Impact Assessment of Trenchless Cured-in-Place Pipe Renewal Method for Sanitary Sewer ApplicationsKaushal, Vinayak / Najafi, Mohammad / Serajiantehrani, Ramtin / Malek Mohammadi, Mohammadreza et al. | 2021
- 21
-
Together We Are Better: How Using CMAR Project Delivery for a Multijurisdictional Transmission Pipeline Benefits the Owner and the CommunityWicke, Jon / Gossett, Michael D. / Pool, Steve / Lemaster, Keith et al. | 2021
- 31
-
Utility Coordination in Alternative Delivery Methods for Transportation Projects: Utility Responsibility Matrix and Design Development—Lessons Learned from Detailed Design Process and ConstructionBarrera, Juan Camilo / Bodera, Tomasz (Tom) et al. | 2021
- 39
-
Critique of CANDE/AASHTO Soil GroupsHoward, Amster / Gemperline, Mark et al. | 2021
- 49
-
An Enhanced Linear Project Resource Utilization Based on Line of Balance TechniqueAlagha, Eid / Bin Mahmoud, Abdulrahman / Altuwaim, Ayman et al. | 2021
- 58
-
Case Study—50% Labor Reduction, 30% Time Savings, and No Damages, No Delays, No Change Orders—No Kidding! Application of 3D Subsurface Utility Engineering per ASCE 38 Standard for Puget Sound Energy’s SR-510 Gas Pipeline ProjectMeis, Philip J. / Haines, Donald W. / Anderson, Shawnté et al. | 2021
- 68
-
Comparison of ASCE’s Unified Approach and Current Practice for Thrust Restraint Design of Continuous Pipelines—Welded Steel Pipe ExampleShumaker, Stephen / Rajah, Sri et al. | 2021
- 79
-
Comparison of ASCE’s Unified Approach and Current Practice for Thrust Restraint Design of Segmented Pipelines Using Ductile Iron Pipe as ExampleRajah, Sri / Shumaker, Steve et al. | 2021
- 89
-
Forensic Study of a 96-in. PCCP Failure in HoustonMcCray, Benjamin C. / Sekhon, Singarpal S. / Wilson, James / Henry, Gregory J. et al. | 2021
- 102
-
Infrastructure Damage Prevention Approaches in the United StatesAl-Bayati, Ahmed Jalil et al. | 2021
- 109
-
Quality Management on Pipeline Projects—Observations from an OwnerSavanyu, Gary B. et al. | 2021
- 118
-
The Review Phases of a Pipeline Design Project—Suggestions for the Reviewer and the RevieweeBeieler, Roger / Chae, James et al. | 2021
- 127
-
Design of a Large Diameter Water Line at Active Fault CrossingLiu, Meng / Ortega, Rafael / Nandagiri, Showri et al. | 2021
- 139
-
Evaluating Welded and Mechanical Pipe Joint Strength for Seismic Design—Part 2: Testing Set-UpSundberg, Chris C. / Tovey, Terri A. et al. | 2021
- 149
-
Seismic Ground Displacement and Pipeline Design Evaluation—A Case StudyLaVielle, Todd H. / Bee, Geoffery / Sariosseiri, Farid / Lang, Yuxin / Havekost, Mark D. et al. | 2021
- 160
-
Safeguarding the Integrity of Large-Diameter Steel Pipelines Subjected to Differential Ground SettlementsFappas, Dimitris / Sarvanis, Gregory C. / Karamanos, Spyros A. / Keil, Brent D. / Mielke, Richard D. / Card, Robert J. et al. | 2021
- 171
-
Seismic Vulnerability Assessment of Water Pipe Networks under Network UncertaintiesRoy, Abhijit / Pudasaini, Binaya / Shahandashti, Mohsen et al. | 2021
- 180
-
Strain-Based Design of a Large-Diameter Steel Water Pipeline Crossing Ground Settlement AreasSarvanis, Gregory C. / Karamanos, Spyros A. / Keil, Brent D. / Mielke, Richard D. et al. | 2021
- 188
-
Experimental Study of a Noncircular Corrugated Steel Culvert at Different Shallow Cover DepthsKearns, Oliver / Moore, Ian D. / Hoult, Neil A. et al. | 2021
- 199
-
Finite Element Investigation of Corrugated Steel Pipe with Extreme Corrosion under Shallow CoverHussein, Husam H. / Sargand, Shad M. / Khoury, Issam / Al Rikabi, Fouad T. et al. | 2021
- 210
-
Investigation of Dynamic Impact Factor of Metal Multipipe Culvert under Shallow CoverKhoury, Issam / Hussein, Husam H. / Sargand, Shad M. / Al Rikabi, Fouad T. et al. | 2021
- 221
-
It’s All True—Solid, Liquid, and Gas Don’t Mix in Inverted Siphons!Tooley, Matt / Beieler, Roger et al. | 2021
- 231
-
Local SSO Requires Regional SolutionsHenry, Gregory / Wilson, Joel / Patel, Hemilkumar et al. | 2021
- 241
-
New Alignment Diverts Near Capacity Treatment Plant to Better Serve Fastest Growing South Carolina CountyYeh, Ashley / Burdick, Geoffrey / Smith, Johnathan / Waters, Mark et al. | 2021
- 247
-
New Bonnybrook Wastewater Treatment Plant Treated Effluent Outfall—Design, Contracting, and Construction OverviewMorales, Juan / Finney, Darren et al. | 2021
- 255
-
Shallow Creek Crossing—Wye Bother? Split It!Bogert, Chris / Barber, Jared / Byrd, Elizabeth / Ryan, Kendall et al. | 2021
- 264
-
To SURGE or Not to SURGE, That Is the Question: Is Hydraulic SURGE Analysis Needed?Ellis, Jesse / Hill, Tom et al. | 2021
- 274
-
A Discussion on Pressure Standards and Its Effect on Water Distribution System Design and OperationGhorbanian, Vali et al. | 2021
- 282
-
Challenges with Maintaining Potable Water Quality—Designing Large Diameter Water Mains for Demands of Today and TomorrowGorr, Brandon / McDermott, Cian / Ng, Joseph et al. | 2021
- 289
-
Changing Regulations and New Developments along a Pipeline Alignment over an Extended Design TimeframeWarner, David / Moon, Alan / Vining, Paul / Nandagiri, Showri et al. | 2021
- 297
-
Designing Concrete Pressure Pipe to Resist CorrosionMueller, Richard I. / Lan, Yan et al. | 2021
- 306
-
Discharged Large Diameter Pipeline for Coal Fired Generation Plant by PE-sGF in JapanMitsuaki, T. / Yoshitaka, W. / Yuichi, S. / Toshinori, K. et al. | 2021
- 316
-
Evaluating Intake Pipeline Hydraulics to Optimize Contra Costa Water District’s Rock Slough IntakePhilipson, Rachel / Ali, Stan / Slezak, Lloyd / Stanisic, Dusan et al. | 2021
- 326
-
Refocusing Design for Water Line Replacement on a Pier Supporting Important Maritime ActivitiesHerckis, Charles et al. | 2021
- 336
-
Fort Laramie Tunnel No. 2 Collapse and Repair—Lessons LearnedMizyed, Numan R. / Duke, Wylie C. et al. | 2021
- 344
-
Getting across a Mile-Long Floodplain: Design and Maintenance ConsiderationsShirk, Jonathan / Blackwelder, Elizabeth R. / Jalbert, Courtney / Gehrig, Jason et al. | 2021
- 354
-
Increasing Redundancy to Prevent Water Service Disruption in HoustonMcCray, Benjamin C. / Ramos, Mackrena L. / Kuruva, Panduranga / Hunter, Anh et al. | 2021
- 361
-
Let’s Take a Second Look: HDPE Piping for Large Diameter ApplicationsLanding, David / Dulay, Marcel P. et al. | 2021
- 371
-
Making Connections to Concrete Pressure PipeRomer, Andrew E. / Mueller, Richard I. et al. | 2021
- 379
-
Northeast Transmission Line 108“× 84” Interconnect—Innovative Design Strategies to Overcome Space ConstraintsKirby, Christine H. / Hernandez, Eric I. / Green, J. Warren / Card, Bob / Tran, Kevin / Chakradhar, Ram et al. | 2021
- 388
-
The Implementation, Outcome, and Lessons Learned of “Design Considerations for Dual 96-in. Water Transmission Pipeline Pig Retrieval Station and Flow Distribution Basin”Tebbe, Joshua / French, Dorian et al. | 2021
- 395
-
Pipeline Triple-Double—Designing for Three Pipe Materials with Two Diameter AlternatesHanson, Hunter et al. | 2021
- 401
-
San Patricio Water Transmission Pipeline—Multiple Pipe SolutionsLeBlanc, Jeffrey / Schwarz, James / Fontenot, Luke et al. | 2021
- 409
-
Scour Power—An In-Depth Risk Analysis for Large Pipeline Creek CrossingsHanson, Hunter et al. | 2021
- 416
-
Swamp Pipeline—Design and Construction of a 66-in. Pipeline in Awful Ground ConditionsEngelskirchen, Eric / Williams, Travis / Sharbono, Chad / Stubblefield, Amanda et al. | 2021
- 425
-
The Challenge of Air Valve Selection in Pumping SystemsRamezani, Leila / Daviau, Jean-Luc et al. | 2021
- 437
-
The Story behind Alberta’s Longest Regional Water SystemWeninger, Stephan et al. | 2021
- 446
-
Updated and Advanced 3rd Edition of AWWA’s Manual 23 Provides Consensus Guidance for Designing and Installing PVC PipeWalker, Bob et al. | 2021
- 457
-
Welcome Neighbors! Upgrading an Existing Regional Water System to Extend the Service FootprintPeel, Breagh / Weninger, Stephan / Ke, Johnny et al. | 2021
- i
-
Front Matter| 2021